Imagine a three-lane highway with barriers between the lanes. One lane is jammed while the other two have room. Before building a bigger highway, could we find a way to let traffic change lanes?

That’s Charlie Murray’s analogy for a distribution-grid problem that can leave capacity unused while developers face expensive upgrades and long interconnection delays.

Charlie is the founder and CEO of Switched Source and a former Invenergy engineer and developer. While working on energy storage projects, he recognized that some capacity needs could be met by accessing underused infrastructure nearby. His team now builds power electronics that dynamically balance the three phases of a distribution circuit. Where imbalance is the limiting factor, that can make room for more load or generation without replacing the existing lines.

Charlie explains what developers should ask when an interconnection study comes back with a costly upgrade, why distribution constraints differ from transmission bottlenecks, and how a more automated approach changed the product his company brought to market.

Getting utilities to trust unfamiliar hardware also required years of customer conversations, field experience, and persistence. Charlie shares how grants sustained the company’s development, why scaling sales and operations eventually required equity investment, and how checking investor references helped him choose the right partners.

For developers navigating interconnection and founders building hardware for demanding customers, this conversation offers something practical: better questions to ask before committing more time and capital.

Charlie also shares the challenges of bringing an entirely new hardware technology to an industry where reliability is non-negotiable and customer trust can take years to establish.

Expect to Learn:

🔹 Why a single overloaded wire can trigger expensive infrastructure upgrades
🔹 How dynamic phase balancing unlocks 10–25% more load-serving capacity
🔹 What developers should ask utilities during interconnection studies
🔹 How power electronics could reduce reliance on traditional grid upgrades

Discover how much more the grid you've already got could deliver.

RESOURCES:

Connect with Charlie Murray:

Check out Switched Source:

‍

This Podcast is Free For You
Thanks to Our Sponsors

The following are Corporate Partners who have helped make SunCast possible:

Platinum Sponsor

The following are Corporate Partners who have helped make SunCast possible:

Noteworthy Quotes:

Charlie Murray  00:00

We should also be able to move those electrons and share them between substations, and have sort of this like homogeneous picture of these you know rings, where it's like yeah, it's harder to get the solar into the downtown, but maybe the downtown breathes in, it kind of inhales, and we're able to help transport those electrons in through the distribution system without sacrificing reliability. And I think that's something that like we want to get to. It's like utilities again are planning for worst cases. They're planning for that summer peak, and we want to see you know more leverage of the full assets on a day to day basis. You know, getting the electrons or oxygen, you know, where it needs to go, and creating tools for utilities so that the grids can be more flexible and dynamic. You know that's like a maybe like a 10 year vision sort of thing, but I think we're pretty darn close.

‍

Nico Johnson  00:45

Welcome back to SunCast. I'm Nico Johnson, your host. Thank you for giving us the only non renewable resource you've got. Of course, that is your time. I promise today we're going to take good care of it, give you a great return on that investment. Welcome if you're a new listener or viewer. If you're on YouTube, would love it if you would continue perusing the nearly 1000 episodes we have here on SunCast. I promise that you, as many others have been, will be well served if you're on the path of building your clean energy company or career. Because we've made an entire decades worth of content to serve your interests, help you come along that path. If you've ever developed a solar project or financed any energy storage, or even tried to connect a major new load to the distribution grid, you know how quickly an interconnection study can change the economics of a project or delay a project altogether. But there's a part of that story that rarely gets explained. We spend a lot of time talking about transmission capacity, far less attention goes into the physical constraints inside the distribution system itself, where much of the investment required to connect new loads and resources actually happens. My guest today, Charlie Murray, is an electrical engineer, former Invenergy executive, and the founder of a company called Switched Source, which is developing power electronics technology specifically to make existing distribution infrastructure work harder and smarter. Today, we're going to unpack the engineering, the economics, the entrepreneurial decisions behind that mission. Buckle up, let's dig into another powerful conversation here on SunCast. Hey, Charlie, it's so good to see you, man. Thanks for taking time out of your busy day to join us on SunCast,

‍

Charlie Murray  02:21

Nico. Appreciate you having me. I'd love it

‍

Nico Johnson  02:23

if you take me back to that time at Invenergy. What did that experience teach you about how utilities actually make decisions with regards to how the grid works? This thing that most of us take for granted.

‍

Charlie Murray  02:35

My experience there is a little bit stale. Things have changed and kind of moved in. I would hope a pretty positive direction, but back then, you know, the the elephant in the room for us was interconnection costs, and yeah, we were doing a lot of renewable integration. We were doing a lot of you know combined cycle generation too. We were also on the bleeding edge of energy storage, and I think that was a particularly interesting area where at the time utilities weren't totally comfortable with how to study these things. Specifically with energy storage, there was this concern about you know what if it appears as a load during my peak time of load over the course of a year? It's like well, the battery's supposed to be helping you then. You know, it's supposed to be discharging energy at that point in time. So you're you're actually kind of making a a worst case worse with this device, which is not how you would dispatch it. So I think we've we've seen that utilities have have come a long way in terms of studying these things, still using you know much of the same toolset in terms of the different software packages. But we're seeing that some of the assumptions around how they're going to behave are are changing and getting a little bit better. But yeah, long process and can quickly result in millions of dollars of extra costs that can burden projects.

‍

Nico Johnson  03:46

You know, I'm curious if there's anything from sort of your observation, both during and after, about the economics of utilities that maybe you came to appreciate and understand that most of us as outsiders might miss about sort of the way utilities work.

‍

Charlie Murray  03:59

You know, when we're talking to utilities today, and then also kind of back then, the speed at which they need to respond to interconnection requests, the volume of interconnection requests, is something that a lot of utilities have been wrestling with for you know the last five to 10 years. So there has been some acceleration in terms of these requests, there's additional processes that they're trying to put in place to fast track things, you know, above or below specific thresholds in terms of how many kilowatts or megawatts you're trying to connect, right? And and I think they've gotten a lot smarter to that end. And at the same time, the models that utilities are using to make these decisions are largely imperfect. They're being informed by better and better data sets, leveraging AMI, and we we still see that you know utilities have you know they have large collections of infrastructure that they're trying to manage. It's a different skill set to move incredibly quickly on one thing than it is to manage. Manage 1000 things very well, and so it's it's tough to have a culture that does both of those things very very well. And you know, a lot of utilities are again trying to move in the right direction there, but it's it's tricky.

‍

Nico Johnson  05:11

Yeah, and with distributed energy and the way that this resource actually interacts with the grid, the general planning cycle for utilities has been turned on its head.

‍

Charlie Murray  05:23

Absolutely, you know it's it's one of these things where you know I think utilities historically were planning on three to five year cycles. That's kind of what they would do with a lot of their integrated planning in the rate cases, and you know a lot of developers are hoping to see answers. You know closer to that you know couple month, three month, six month time frame, depending on where they are on the grid, that is a big change. And I would say there's there's also even larger changes when it comes to this concept of you know you start to aggregate smaller technologies that you're going to have connected on the customer side of the meter, and they can get aggregated up into pretty significant quantities, and it's one thing when the utility is in the driver's seat for a large load connection, and they can kind of set the pace, they can study it. But things that are popping up behind the meter, and we see this a lot with electrification. So you know, EVs, some energy storage, some rooftop solar, as well as electric heat in a lot of different jurisdictions, and maybe some jurisdictions that would surprise you, even kind of getting into the the deep south where they're they're leveraging electric heat. That load growth can really blindside a utility because it's not like they get a one year warning that this project is going to come online.

‍

Nico Johnson  06:36

You said AMI. What do you mean when you say AMI?

‍

Charlie Murray  06:39

So advanced metering infrastructure. We've seen a lot of utilities invest in this to get better real-time data about what's going on down at the customer level, and then you know utilities have figured out ways to incorporate that into their planning in certain places. Other places, it's been more focused on you know how can we create better rate structures or you know accommodate different rate structures down at the meter level and do time of use and things like that. So you know, there's there's a lot of technology that's moving towards the grid edge, and on a utility by utility basis, it changes whether or not that's being incorporated back into the actual distribution planning efforts and how they make decisions about what can connect to the grid, you know where and when. There's a conversation right now on capacity, and and I think a lot of people are talking about capacity, how the grid edge can help with capacity issues at that ISO level, and then there's this other piece of it, which is more tied to the interconnection, you know, request type problem, interconnection upgrade type problem, which is you okay? You need this balance of resources. We need the electrons, you know, down at the customer level. We need electrons to be generated. A lot of them are generated up at the ISO level. And then there's sort of like the piping of like, okay, how do we get it from point A to point B? And and we usually use this blanket term of like, oh, we need capacity to be able to do this. And there's there's really like two forms of capacity. It's like, do we have the electrons, and then do we have the pipe, the wire that we can actually push them down without, you know, thermally overloading the wire, blowing it up, having such bad voltage quality, so you know, voltage drops. So like, there's there's a lot of unfortunately like nitty gritty details that we have to unpack to to kind of understand how those two can play with one another.

‍

Nico Johnson  08:22

To your point about capacity, capacity market is this like think of it as like standby power to if every light in the United States turned on, if every HVAC turned on, if like everything you pop, I often think somebody explained it to me with water instead of electrons. Yep, the capacity market is the size of the tube the engineer requires you put to feed your house in the event that you turned every faucet on and every single device that could pull water is pulling water at the same time? How big would the pipe going into your house need to be to not constrain the potential of every faucet? That's capacity, right? And then there's resource adequacy. When really get down the rabbit hole, that which is like, well, where does the water come from? And do we have we procured enough of it? Is it the local? Is it a well? Is it the local reservoir? Is it water tanks supplied throughout town? Do utilities have a tremendously difficult job trying to solve for a problem that is almost unknowable. Like how many people are going to turn on all their water faucets or all their appliances in a given moment, and how do we ensure in that moment we don't have rolling blackouts or brownouts, so that such that we can serve the load responsibly and reliably, and people can continue to live oblivious to the reality that this stuff is made somewhere and delivered to them.

‍

Charlie Murray  09:49

Yes, and I would say you know at the transmission level of the grid, and also with generation, there's a lot more redundancy that's built into that math, right? Like because when things go wrong. At that level, you're not talking about you know oh we got 10 customers without power or 100 we're talking you know potentially millions, right? And it and it goes sideways really really quickly. Down at distribution, the system is actually more of a one way delivery system than it is this network. Yeah, and and so just from a planning perspective, it's it's run closer to its fully loaded capacity, like what it can do more of the time.

‍

Nico Johnson  10:27

Yeah,

‍

Charlie Murray  10:28

and and I think what we see when we look at data sets from utilities, both on the loading side as well as on the generation side, and this changes regionally, right? You know, we see this kind of in the Southwest in terms of distributed generation, where a lot of the utilities there feel like they have taken all they can take in the Northeast. You know, with electrification, there's a lot of forward-leaning, you know, regulators that want to see electrification embraced. They want to see decarbonization, especially pointing at EVs. Yeah, and they're telling the utilities like, "Hey, accommodate this," and they're looking at the amount of headroom and capacity that they have on their distribution systems, and saying like, "Hey, we're at like 8085, 90% on like a large chunk of our circuits. Like we we have this great dataset that we look at for a utility in the Northeast that we can share, and it says something like 50% of their circuits only have 20% of headroom.

‍

Nico Johnson  11:18

Yeah,

‍

Charlie Murray  11:19

and it's like 50% of circuits. Let's say that you have to go out there and touch, rebuild those types of circuits. The amount of dollars that you are talking about is not hundreds of millions. It's like 10s of billions. Yeah, like it is. It kind of breaks, you know, the the rate recovery structure type system of just like, oh, we'll just put this into the normal rate case. We'll plan for it, and we'll slowly do upgrades.

‍

Nico Johnson  11:42

We'll yeah, we'll build it out over the next 1015 years.

‍

Charlie Murray  11:44

Yeah.

‍

Nico Johnson  11:46

Now, the good news, and we've said this for years, is there are certain places in the world that are postcards from the future, now past, like Hawaii and Puerto Rico, where these kinds of nodal grid constraints presented themselves years ago, right? So there are these little microcosms of markets, like Nico in Hawaii, that have figured out how to address it. Lo and behold, something that you've spent a lot of your career thinking about, they turned to this electron storage device, not unlike the water container that one in Latin America might see on every house, right? Like I used the analogy earlier for a reason. I used I was a Peace Corps volunteer living in Guatemala, and on every single house there's a water tank, and there's a water tank because there's there's not a useful, especially in rural areas, water distribution system, and so even if there is one, homeowners buy a water tank. They store water in that tank so that if the municipal water turns off, they've got water that they can wash and cook with. In Hawaii, you couldn't get onto at a certain point. You couldn't interconnect at a nodal level without batteries because the utility needed you to be the local storage device for the electrons to ensure that they didn't have to send them to you in a peak period, sort of net capacity. You started working on energy storage well before it became this sort of obvious answer to every grid constraint and this like cornucopia panacea of like it's going to solve our problems. What problem were you trying to solve when you started really digging into energy storage back in the energy days.

‍

Charlie Murray  13:24

So back in those days, we were really chasing this market around the PJM fast regulation, which you know there had been a market that was established. There were price signals that were were kind of you know allowing batteries to play to balance out you know, load and generation because we're we're always trying to balance out load and generation, and we have some slow moving resources that do that pretty well. And then the idea was, well, like take that volatility, that like extra layer of noise and volatility that you have, and let the batteries chase that signal because they're going to do it better than a peaker plant would. And and that's true from a technological perspective. They're you know they would. They created this market, and it was kind of a you know a pretty exciting time in the energy storage world because it was like, oh, they're putting a real value on energy storage. You don't have to put a long duration battery because with energy storage, you've got the front end of this, which is what connects to the grid, power electronics, and inverter, and then you've got the battery sitting behind it, and you can, you know, we talk about energy storage frequently in terms of duration, which is like how long could you run that energy storage system flat out before you run out of of juice inside of it, right? So the more that you shrink the duration, the lower the cost of that system is, because the battery is where a lot of the costs are, and it's variable with how long you want to be able to discharge it for. Right, so the fixed cost is that that power electronics front end, and what was nice about this market is it allowed you to use like a 15 minute or a 20 minute duration battery, which meant that your your costs were actually pretty low. And the payment was, you know, such that you can make money on that. So we built out a significant amount, over 60 megawatts of energy storage for that fast regulation market, and that was an exciting time to just, you know, get batteries in the ground quickly, understand how they work, you know, play to their strengths, which is moving fast. And then after that market, that was when I was tasked with like, hey, go figure out a way to use energy storage to help utilities and sign up bilateral agreements with utilities. And there were a few key obstacles that we were running into. You know, one was physical size. You know, energy storage systems, they are you know, physically large. The energy densities continue to get better, which is phenomenal. But you you do have to find room for for a decent size footprint,

‍

Nico Johnson  15:49

often in urban environments.

‍

Charlie Murray  15:51

In in urban environments, which kind of leads to the next thing, which is you know the safety concern. And and again, I think you know folks have gotten better at at mitigating safety risks associated with batteries. But if you've seen a lithium-ion battery, you know fire, it's still you know pretty anxiety-provoking. Right. The last issue was a regulatory question, and I would say the regulatory question in the last 10 years has largely fallen away. Where I think we've seen a lot of regulators and utilities agree with, like, hey, these are the use cases. You know, get after it. Go and and deploy these things. And utility, you can own some portion of energy storage that's on your system, and also we're going to have third parties like developers own some energy storage. So those were the three challenges that I was working on that seemed really, really hard. The sort of solution in my mind was like, well, let's let's keep what's nice about the energy storage system, which is like having some controllable capacity, and instead of having the battery sit behind this, let's just have a different piece of infrastructure, a different wire on the system, or a different distribution circuit sit behind that controllable gateway, that power electronics device, and you shed the regulatory concern. You get rid of a lot of the fire risk, and the price goes down, the physical footprint goes down, and so it was like you can theoretically discharge or leverage this other piece of capacity for an infinite duration, and the cost doesn't scale infinitely. The cost is just that cost structure of the power electronics. That was kind of how we we stumbled into this.

‍

Nico Johnson  17:17

At what point did you realize that you might not need a battery at all to solve some of these problems, as you're alluding

‍

Charlie Murray  17:22

to. Okay, so that's a really good question. Nobody's ever asked me that before. We were looking at these solar hosting maps. If you're familiar with these solar hosting maps, you different utilities publish these things, and it was a way to guide developers so that they didn't come to the utility to try to connect solar to a circuit that could not accommodate it, and a lot of times, what is in the guts of these models of like how much solar can a circuit take is just how much load is on it, right? Because the the utility sort of business model of sending things down the pipe and all the sort of regulation automation, that's all kind of designed in this one-way system, so things start to go again. They go sideways when you're you're pushing things back up the pipe. Can be done. Utilities have accommodated it. Don't want to poo-poo it, but just like it, it can get hard for certain folks to wrap their heads around. So coming back to it, the solar hosting maps are just we're going to create these heat maps that show where you can connect more solar or less solar, and kind of guide the developers. When you look at those maps, you will not see a sort of like homogeneous, like oh, this whole region, like the downtown area, is green, and then it gets red, you know, as you go farther out into more rural areas. Like that's that's kind of what you would expect intuitively. Is like oh, we have high load penetrations during the daylight hours in downtown areas, and it's hard to develop solar there, you know. And then, you know, you get to the outskirts, and it's like, well, it's red because it's easy to develop solar here, so a lot of it's been installed, and there's not a ton of load, so there's not a lot of incremental that we can connect. Instead, what we saw when we looked at those, was this complete like hodgepodge of different colors of circuits, and and that was the aha moment for us, where it's like, oh, there's an arbitrage opportunity here. It's tough to balance the loading and balance the solar between circuits, and that was where we started with this concept of, you know, we're gonna we're gonna push on, you know devices that can do that that dynamic balancing between parts of the infrastructure that utilities don't have a good tool in the toolkit to do it today.

‍

Nico Johnson  19:30

Charlie, I want to explain something that maybe even experienced developers misunderstand. Can you help us understand the difference between transmission and distribution? I mean, you're using a word circuit that I'm not sure I could describe to someone.

‍

Charlie Murray  19:42

Yes, absolutely. So, at the transmission level, we have a network of sometimes we call it lines, but we have this network where we're connecting different substations, connecting different generators, and it's a spider web. There's all these different connections and nodes, and there's substations that have you know two lines coming in and. Two lines going out and a connection to a generator, all these different things that are connected to multiple nodes. At distribution, we have a connection up to you know a sub transmission or a transmission level.

‍

Nico Johnson  20:11

Yeah,

‍

Charlie Murray  20:12

but distribution is a hub and spoke system. The hub is the distribution substation where we step down from the transmission level voltages to something that's like most common is like 15,000 volts. Now we are at the wood pole level of infrastructure. You know the sort sort of stuff that you see where it's you know three wires across a cross arm wood pole, you know 50 feet high alongside the road. Not the big steel lattice towers. Distribution utilities to give you a sense of scale. Decent-sized IOU investor-owned utility has about 1000 distribution circuits that they're managing, and this is kind of the unit at which they think of when they're thinking about planning the system.

‍

Nico Johnson  20:51

Right.

‍

Charlie Murray  20:52

A big utility like a ComEd or Southern California Edison might have four or 5000 of these distribution circuits.

‍

Nico Johnson  20:58

Yeah.

‍

Charlie Murray  20:59

That distribution circuit is a delivery system from the substation out. You might be anywhere from five to 10 miles long. There might be somewhere between 500 to a couple 1000 customers that are connected to it, and this is the part that really starts to get complex.

‍

Nico Johnson  21:15

It's the last mile.

‍

Charlie Murray  21:17

It's the last mile. It's there's three wires that are leaving the substation, we use three-phase power. Everybody thinks everything's just three-phase power. When you look up at that pole, you see three wires. When you see transmission lines, a lot of times you'll see multiples of three of wires that you see, you know, on transmission lines. At distribution, this falls away. So there's there's three wires across the top. We use those three wires when we're feeding a Costco. At your and my house, we have single phase power. We're fed off of a single phase tap.

‍

Nico Johnson  21:49

Yeah,

‍

Charlie Murray  21:49

and so the utilities have this three phase backbone and then single phase laterals that they use. And and the whole point of this was like, if we run all three wires to every home. It's going to be too expensive. There's a more cost-effective way to do this.

‍

Nico Johnson  22:04

Yeah,

‍

Charlie Murray  22:05

we're going to use these single-phase lateral taps. What ends up happening is it's really difficult to evenly load your backbone when you leverage single-phase taps. That is not the utility's fault. It's a design decision that was made before any person at a utility right now was born, and and it's something that exists across the United States, and what we see is there's a significant amount of lost capacity, both in terms of connecting distributed energy resources as well as connecting load, because whatever your highest loaded phase is, whatever your highest generation phase is that is going to be the trigger for you to potentially upgrade all three phases, all three wires. So you you might have a constraint that's on one piece of this infrastructure that comes in threes, but you're going to have to eat the cost now of all three. Yeah, and and that is the the type of problem that our technology was really well suited to solve was just this idea that we can flatten that imbalance across the three phases, unlock 10 to 25% more load serving capacity by balancing out that electrical stress across the pieces of infrastructure that are right there, and then lower those costs for new loads and new generators.

‍

Nico Johnson  23:22

For anybody listening who is not an electrical engineering nerd, they're still kind of scratching their head. What is Charlie talking about? I've heard you describe the distribution grid and the way that you just outlined it as instead of three wires, a three-lane highway with kind of barriers between the lanes. Walk me through that analogy. Help us really understand the future you envision, and I'm going to come back around to sort of like how did obviously you worked at a utility, like spend time thinking about this, but like the operator and entrepreneur in me wants to know how did you come up with a business to try and solve that. But first, like explain the analogy to me.

‍

Charlie Murray  23:55

At the distribution circuit level, we have that three phase backbone. We say it's similar to a three-lane highway where you have barriers between the lanes, and this is just representative of the physics of the electricity. Those three wires, there is no way to share loading between the three wires. If you have that three-lane highway with barriers between the lanes, you can't equalize the traffic. And then the the analogy for the single-phase laterals is think of it as an off ramp from one lane, and you can kind of pick your lane. You know, you might have to to always ride the middle lane on the way home because that's where your off ramp is to go to your neighborhood. That's kind of how electricity works. Is we have these off ramps that are just connected, somewhat arbitrarily, somewhat to maintain balance to the individual lanes. So that is how the the system is set up, and what we are looking at is like this is a really complicated optimization problem because we are not. What we want is we want perfectly balanced traffic, and what we have control over today, you know, without switch source and without our device, is we can. Connect the off ramps to different lanes. We can try and say like, hey, you know, last season's traffic or last year's traffic was in such a way we should really move this off ramp from the middle lane to the right lane, and then you can see how it plays out.

‍

Nico Johnson  25:12

Is that something that's connect that you can connect digitally? Like, what happens when one lane gets congested?

‍

Charlie Murray  25:17

So when one lane gets congested, there's a few things that happen. One is you're going to thermally overload that conductor, and you're going to overload everything all the way back into the substation.

‍

Nico Johnson  25:26

Conductor is a fancy word for wire.

‍

Charlie Murray  25:28

Wire, yes. And I mean, what what I think you know, we we we talk to a lot of engineers even that that kind of appreciate this, but like even going all the way back up to the transmission level, the substation transformer, which is this pretty darn expensive asset, is rated, meaning like it what you're allowed to use it for without really taxing it. It's rated on a per phase basis, and so yes, it is. It's like the rating assumes perfectly balanced power, and there is no perfect balance down a distribution. And and so you know, getting back to the the sort of traffic analogy is like utilities can go out there and they can try to take a tap off of one phase and reconnect it to another one. You're causing an outage for all the customers that are on that tap, and then you have to kind of wait and see, you know, when to to balance that out again. A

‍

Nico Johnson  26:16

tap is just like connect physically connecting into a wire at a place where it wasn't originally intended to be connected.

‍

Charlie Murray  26:22

Exactly. Yeah. You know, and it's it's a lineman in a bucket truck that are doing this. There's a lot of operational challenges that complicate this for utilities.

‍

Nico Johnson  26:29

Yeah.

‍

Charlie Murray  26:30

So if you think about a storm type scenario, you know, linemen are going three through trying to reconnect taps that have might been knocked down by trees and things like that. You know, they don't have the toolkit to do some sort of complex analysis of, you know, what is the system status today? What is it going to look like tomorrow? What is it going to look like in the next year? You know, when I'm connecting this tap, and so a lot of linemen are just like, well, we need to connect this tap. We're going to connect it to whatever is the safest phase for us to reach, which is typically the one that's on the roadside. Yeah. So we see a lot of just like operational habits and kind of safety things that play into this as well, where just ends up having a really imbalanced system down at the distribution level, and there's just not a good tool to solve for

‍

Nico Johnson  27:12

it. So maybe we've buried the lead here. You at some point saw, as I said earlier, that maybe a battery isn't the best tool to solve this congestion problem? As as you started looking into it, I'm curious: was there anything that was like a first alternative you envisioned for how to address this congestion problem that you were seeing?

‍

Charlie Murray  27:36

When we looked at it, it came down to the cost structure of the solutions, and and that was where it was like the the opportunity is difference in loading between circuits. That's where we started. It was there's a difference in loading between circuits, and that was kind of like the wall. It's like this is free

‍

Nico Johnson  27:54

energy because it's sitting here as a capacity.

‍

Charlie Murray  27:56

Exactly, it's free capacity, you know. And then the the ladder for that wall was just, you know, hey, the power electronics. Like, think about this: if you're, you know, if you're going to use an energy storage system, and this was something I kind of glossed over earlier too, is like after the PJM fast regulation market, the thing that everybody was chasing with energy storage was upgrade deferrals.

‍

Nico Johnson  28:18

Yeah,

‍

Charlie Murray  28:18

you know, and and then that got rebranded as non wires alternatives, and it got you know rebranded now and kind of broken up, and it's kind of like VPPs. It like every four years it gets rebranded, but it's really easy to make economics pencil for energy storage if you are looking at deferring the upgrade of these wires,

‍

Nico Johnson  28:37

right?

‍

Charlie Murray  28:38

Because they're it's million dollar projects; they get away from you really really fast in terms of costs, and so that's what I was chasing. You know, at at Invenergy was like we need to go find these upgrade deferral projects,

‍

Nico Johnson  28:49

right?

‍

Charlie Murray  28:49

And then it came down to the cost structure of the the the solution, the solve, which was an energy storage system. You're always going to be paying for the power electronics and the battery, and something like you know, 80% of the costs can be in the battery, depending on how much duration you need. And I was like, well, why don't we just try and solve it first by using the capacity in the other wire with a cost structure that's you know 1/5 to 1/10 the energy storage. That was the the aha moment.

‍

Nico Johnson  29:16

Yeah. So to the next step from the aha moment is you start to formulate a plan for creating a business around it, were there non-present alternatives, like kind of a first or second shot at trying to solve this problem that you addressed first? And I'm curious if there were experiences or a specific project maybe that changed how you thought about the solution.

‍

Charlie Murray  29:35

We started off again with this concept that we were going to balance from one distribution circuit to another distribution circuit, and that data was publicly available in one way or another through these like solar hosting maps and load hosting maps and things like that. And then when we started talking to utilities, what you know we we kind of chased down this road. Like we we found a technology. There was a university that was working on something that was a really good fit for medium voltage power flow control. Okay, we were able to. Get some support from the federal government through an organization called ARPA-E, the Advanced Research Projects Agency for Energy, and that supported us in our early days of like, hey, we're going to chase this idea. We think there's a huge opportunity here, and there were some utilities that really wholeheartedly agreed with us, and they they really saw it and they got it, and they were standing alongside us and trying to figure this out. And then as we got closer and closer to to kind of deploying that solution, we found it's like, well, on paper this all makes sense, and yet operators are going to have to tell this box what to do, yeah, and they're going to have to dispatch it right. And for us, that was something that was like that is a big impediment to scaling this technology is there's a very steep learning curve for for dispatchers to be able to accommodate this. It's the sort of thing where you want to integrate it into you know like a DERMS type system, distribution energy resource management system, or an ADMS, an advanced distribution management system, software packages that help tell boxes on the grid what to do. That can be a big lift, and that was where we started to realize: is like, well, if you look one level lower in the distribution circuit and look at the three wires, there was this other opportunity that was a more automated opportunity. The box can sense what it needs to balance at the box, and you just set it and forget it. It was like, okay, this is this is going to scale quicker, and and that's what we found.

‍

Nico Johnson  31:25

Okay, so it's a distributed electronic product. Well, I'm curious what the first design looked like. What assumptions did you need to prove at the at the line level that this could work? I mean, I'm still not sure how you knew it was technically possible to be able to switch lanes with electrons, metaphorically speaking.

‍

Charlie Murray  31:40

Yeah, I mean, we we spent a lot of time thinking about you know how to do it from a power electronics perspective and what parts of the problem we could solve with the power electronics. And you know, you get into feature creep. You know, you can design power electronics to do a lot of things, and then it comes down to like, well, how much money are you willing to throw at the the solution, and does it get clunky? And and that was a lot of back and forth with utilities, and and I would say you know for especially for other entrepreneurs that are listening to the the call here, it's like establishing dialogs with utilities is really really hard and also really critical if you're going to build a tool like this.

‍

Nico Johnson  32:15

Yeah, you got to figure out who in the utility you could talk to. You had the advantage of having come from once.

‍

Charlie Murray  32:20

Yes, and and and it's one of those things where like that can take you three months,

‍

Nico Johnson  32:23

right?

‍

Charlie Murray  32:23

I mean, it can take you longer than that. And we participated in a lot of really phenomenal incubator and accelerator programs. You know, the first one that we did out of the gate was with was with Amarin. We had some other notable ones. There's one that's supported by Green Mountain Power. We did one with associated with Duke called Jules. We did one, you know, that was probably one of our favorites was 35 mules with Florida Power and Light, and so we we participated in all these incubators. And the the point of it wasn't like, hey, we're going to leave this with a sale. The point of it was like, we are going to establish a rapport so that we're making the right product.

‍

Nico Johnson  33:00

Yeah,

‍

Charlie Murray  33:01

and and that was something that we spent years making sure that we had those relationships to to make sure we were on the right path.

‍

Nico Johnson  33:11

Can ask a clarifying question around the sort of the challenge of power electronics. The only time I've ever really heard anybody mention power electronics is at low voltage levels, like you know, in phase sort of introduce module level power electronics to the solar industry. What changes when you're thinking about power electronics at the 15 to 27 kilovolt level?

‍

Charlie Murray  33:30

So it's it's a big challenge of like you're you're typically using the same components that those folks are using. You're just stacking them in topologies where you can connect to much higher voltage levels, and so the you know the basic components like the capacitors, the IGBTs, you know silicon carbide chips, whatever you know is kind of like the de jure subband conductor, the sort of like commodity off the shelf and like the the unit where you get the best pricing, the best bang for your buck tends to be at these lower voltage levels, 1200 volt, 1700 volt things that are used in more industrial or on like solar inverters, energy storage inverters with 480 volt output, and then it's on organizations like ours and our you know incredibly bright engineers to say, hey, like this is what it would have to look like to be able to connect to a 15,000 volt line and control power flow, and there's there's always two pieces to the power electronics. There's the like, okay, this is how we have to build it so it does its job, and then this is how we have to build it so that it can tolerate faults. And distribution systems have lots of faults. Like you, if you look at where interruptions come from and the types of interruptions that we experience, wood pole level infrastructure is where it happens, and and that is that's just like a truth. You know, you can look at the data when you are connecting directly to the primary to those medium voltage systems. You do not have a lot of buffer. So, like for example, if you're a solar inverter, typically. You're connected to the grid through a set of fuses at the pole. There's surge arresters at the pole, and then there's a transformer which also absorbs all of the, you know, sort of like lightning high voltage transient type impulses, yeah, before it even reaches your box. Yeah, so it it is a big lift, and you know these were all like learnings that we had to like hard knocks that we like absorbed over the years. But it's hard to make something that connects directly to the primary of a distribution system. It's just really tricky to do.

‍

Nico Johnson  35:32

So you know, Mike Tyson famously said, "Everybody's got a plan until they get hit in the face." Yeah. What happened the first time you connected your technology to a real distribution grid?

‍

Charlie Murray  35:41

Yeah, I would say the so the first time you know we we had some luck where where it worked really well. We were in upstate New York. We were working with a municipally owned utility. We had some support from Nicerda, which again, for for your energy entrepreneurs out there, you know, there's there's a lot of great states, and we have a soft spot in our heart for New York and Nicerda, super yeah, they're super

‍

Nico Johnson  36:03

investors. They're early believers.

‍

Charlie Murray  36:06

Early believers, you know, they care. Just good people over there, you know, and they've they've got financial

‍

Nico Johnson  36:13

support,

‍

Charlie Murray  36:14

yeah, financial support to really, you know, kind of like get ideas off a page and into hardware, and and so that was the project we were working on, and I would I will tell you that um we we got that unit up and running, and I would say the scariest moment was like something else happened on the distribution circuit, you know, two miles away from us. But because we're the new weird device on the circuit, everybody's looking at us like, what did you guys do? How could you have you know like how how could you have caused this transformer to fail like two miles away from us? And it's like we like we we spent a lot of time thinking about it and you know trying to to get comfortable with them. We were just like like we didn't. But when you are that new wonky thing on the circuit, like all eyes are on you, even if it it's you got to do a lot of mental gymnastics. You know, other than that, you know that unit ran, still running today, runs great. One of the the things for us has been like we we really wanted to have success early days, and we knew that the utilities all talk to one another. Oh

‍

Nico Johnson  37:14

yeah, of course.

‍

Charlie Murray  37:15

And so it was like you know the the bar is really really really high, and so that was something that like we we kind of made sure that the equipment we designed it to be utility grade.

‍

Nico Johnson  37:27

Yeah,

‍

Charlie Murray  37:27

which is not what I think. Um, it's like a little bit different from my previous life. You know, at at Energy Developers was like, yes, you absolutely had to have a device pass technical due diligence. Yeah,

‍

Nico Johnson  37:40

had to be UL certified,

‍

Charlie Murray  37:42

yeah, those sorts of things. And then at the end of the day, it's like if you still were feeling uncomfortable about the technology, it was like you were going to solve that legally. You're going to solve that contractually, and that's that's kind of a different mindset

‍

Nico Johnson  37:53

than the

‍

Charlie Murray  37:54

utilities, which is like they have to get very comfortable with the hardware and the technology and the performance of it. Yeah, they don't want to. Yeah, they don't want to hear a piece of paper. They buy,

‍

Nico Johnson  38:02

yeah, they buy into the like nobody ever got fired for hiring IBM, right? Like that's the that's the utility mindset, and that's why I was saying somebody recently who's new to the industry, and they're like, "Who's ABB?" I was like, "That's hilarious! If you've been in the industry sector for very long, you would know who ABB is." They hadn't because there are like maybe five country companies globally that participate in the market in the way that ABB does in terms of switchgear, etc. Schneider among them, but it really does come down to the trusted few, and you're fighting your way into the trusted few with a device that's completely new and untested. And that's one of the things I was sort of pulling the thread on here. But I'm curious for the for folks who can't so wrap their head around like what does this actually look like? What I understand what a solar inverter is. How does this piece of power electronics like look similar or different, and where does it sit?

‍

Charlie Murray  38:55

Yeah, it so it looks a lot different, and this goes back to the utility grade and and kind of a maybe kind of a silly thing, but like a sacrifice that we we had to make with the the actual technology and how we would like to engineer it. So I'm sure you've driven down the road and seen one of those you know green utility boxes, like a piece of switchgear. That's what this box looks like. It looks like switchgear that might be a little bit on the big side, you know. So it's about four and a half feet deep, about nine feet long. It goes out on the distribution circuit, so it's not inside the substation fence. It's underneath the pole, kind of where you see, you know, that those green boxes making a street corner. That's where we, yes. And how do you know

‍

Nico Johnson  39:36

where to put

‍

Charlie Murray  39:37

it? Ah, that's a good question. So we we do distribution planning studies with the utilities using those same tools and same software packages that they use. We can show them how to model our device so that they can understand the best place to put it. And the spoiler alert is like about a third of the way to halfway down the circuit is the best place to put it.

‍

Nico Johnson  39:56

And then so does do all three wires run in and then like now. You have a traffic cop inside the box that allows like electrons to shift into different lanes.

‍

Charlie Murray  40:05

That's right. And what's kind of neat about it is like the traffic cop is actually like sitting in a turnout on the on the side of the road. He's not stopping all the traffic and then saying like, "No, you go to this lane. You go to this lane. You go to this lane." So this this box is in we in the electrical world we would say in shunt, but it's it's basically in parallel. It's like teed off. It's a flying tap. Yeah. And so what's cool about that is the box doesn't care how much load you have on one side of it or another.

‍

Nico Johnson  40:36

So you're not redirecting the circuit through the box.

‍

Charlie Murray  40:39

We're redirecting the imbalance. So the box is sized for how much imbalance traffic. So going

‍

Nico Johnson  40:46

okay. So you're pull. I'm going to try this. So like, let's just say there's an imbalance on line one. You can then pull the imbalance volume off line one, go through the box and onto line two.

‍

Charlie Murray  40:58

That's right. So if we have clever, yeah. If we have 200 cars in the first lane, 150 in the second, and 100 in the other, we don't have to be sized for 200 plus 150 plus 100. We have to be sized for the 50 cars we want to shift from the first lane to the last lane, so that everybody has a happy 150.

‍

Nico Johnson  41:17

Yeah,

‍

Charlie Murray  41:17

that's how this box works.

‍

Nico Johnson  41:18

It's also, and I don't know if you've used this analogy, but like the railroad industry solved this with the little thing that shifts between the lanes. You can't physically do that in electrons, and so this is sort of that that mechanical shift between two or three different rails, so that the new cars coming along can get on a different track. Okay,

‍

Charlie Murray  41:37

that's right, and it's not a switch; it's just a solid state connection that can just kind of flow the electrons where they need to go.

‍

Nico Johnson  41:44

You mentioned earlier reaching out and sort of discovering that there was some IP sitting at a university. What what intellectual property came out of all these lessons?

‍

Charlie Murray  41:52

Oh man, loads. So I I will just tell you like there's buckets, right? There's the bucket of like paper intellectual property, which is where a lot of people start right. Hey, I came up with this great new idea. Then there's a bucket of like, you know, we put it out in the field, and you know, dear God, there are so many faults on the system. Like, we have to make sure that this thing maintains uptime. And the only way that you really get comfortable with that is having things run. And like, we, you know, we're beating the drum right now about you know the 150,000 plus run hours that we have in the field, and like the great availability that we have, and like we've gotten there. Anybody who's coming up with like a solid state transformer or power electronics device, it's like you can be the smartest person in the room. To your point, like everybody's got a plan till they get punched in the mouth, right? Like let's bring on our Mike Tyson again. You you have to be in the ring and take a few of those hits to know, you know, like how do you do that? How do you change your game plan? Like, yeah, you're going to still get punched in the mouth occasionally, but you want to like up your game so that it's it's like less and less, and your uptime is better and better. Okay, so that's bucket two. So bucket one, paper. Bucket two, you know, grid faults, and then there's this third thing called interoperability, which is like when you are connecting your new cool thing, you do not want to have to tell utilities, oh by the way, you have to change settings on all your other devices on the circuit. You know, oh by the way, you have to run new wires from this part of the grid to this part of the grid. You have to run fiber optic cable to be able to connect me and control me as fast as I need to be controlled. Like all of those things are project killers, right? And you know you can be pretty smart on the front end, but you're still going to learn something after you get these boxes in the field that helps you from an interoperability perspective. And we have patents covering like interesting things in these three buckets.

‍

Nico Johnson  43:42

Amazing. Before I move to application, how did you fund this? You mentioned RPE. You mentioned accelerators. I mean, I think it's fascinating story because you're not like traditional venture-funded hardware startup.

‍

Charlie Murray  43:55

No, we're not. And I mean, I think we. That isn't to say that like we didn't want to be at some point in time, especially early days, and then there were some some critical points in between where we also wanted to be, you know,

‍

Nico Johnson  44:07

hard tech. And the time that you built this company was exceedingly difficult to fund. By the way, oh yeah, the first five

‍

Charlie Murray  44:12

years, like hard tech, deep tech wasn't a thing. We were called clean tech, and clean tech was toxic. And then we usually started by telling folks those early days with investor calls, it's like they would call us, you know, be really excited to talk, and it was like, okay, we've got three things to tell you before we, you know, blow 30 minutes on this conversation. It's like, you know, one, we're building hardware. You know, two, it's like, yes, our business model is getting paid for that hardware, not on a service model, but like, you know, we we're going to be capitalized by utilities, so they're just going to purchase purchase it. And then you know the third thing is oh, and those customers are utilities. Like that's you know for better or worse, like our technology is very specific to the problem set that that distribution utilities have.

‍

Nico Johnson  44:53

Oh my god, I'm just laughing. Anybody who's ever funded the this industry is just like looking at it, going. Again, answer Nico's question: How did you fund this? Because you're basically telling investors we're going to deploy hard tech. It's not a subscription model, and it's the hardest possible customer in the energy sector.

‍

Charlie Murray  45:10

Yes, that's right. And so, and by the way, we're going to

‍

Nico Johnson  45:13

compete with ABB and Schneider and everyone else.

‍

Charlie Murray  45:15

Yes, and people were running for the exit, you know, and and and like we we had some some interesting folks that kind of kicked the tires on us along the way and gave us some some you know angel type levels of funding. Yeah, a couple 100,000.

‍

Nico Johnson  45:27

Yeah, exactly.

‍

Charlie Murray  45:28

We we largely had to fund this with grants. Yeah, and ARPE really saw our vision. Um, you know, understood that this was a required thing for distribution grids from a reliability perspective. You know, also from a decarbonization perspective, you know, an electrification perspective, and then Serta was a big supporter of us too. Again, for their vision of how they wanted the electric system to grow,

‍

Nico Johnson  45:51

because when they when they are in theory supporting you, ARPA-E and others that are grant-making entities go, oh, okay, they're saying that this is a need, like we can get behind it.

‍

Charlie Murray  46:00

Exactly. It's like

‍

Nico Johnson  46:01

you got to play both sides of the of the equation here.

‍

Charlie Murray  46:03

And I think they wanted to see innovation in this space, and they just saw that venture was running for the exit. Yeah. You know, it's it's like they have this vision for how the grid is going to look in terms of what's going to be connected to it and how reliable it needs to be. And it's like, hey, we need new tools here, and they're looking around at who's innovating, and it's it's tough. So

‍

Nico Johnson  46:19

so lucky, unfortunate you. You've made it how long on roughly how much money that is non dilutive equity.

‍

Charlie Murray  46:26

Yeah. So we we took advantage of that, and then you know it's it's like many things in life. It's like um you know you sort of begrudgingly do it in the beginning, and then you get good at it, and then you kind of get addicted to it. Yeah. Um. So we, I think the the last number I heard was something on the order of like 25 to $27 million in non dilutive funding. Amazing! That's what got us here. And then we we also have a bipartisan infrastructure law grant, which is an additional $49 million. Explain,

‍

Nico Johnson  46:56

folks, to folks what that means.

‍

Charlie Murray  46:58

So the the federal government, originally under Biden, but Trump is is standing behind many of these, maybe not all of them, to push dollars to reliability, resiliency type projects for the grid, and we qualify as that. And we were working with a large utility in the southeast to deploy this technology at scale. You know, so over 200 units. You know, and that was the the sort of premise of that project. It's like, hey, we're going to go and deploy a couple 100 of these to make the grid easier to reconfigure, so we can restore service quicker after storms. That's a big project that's still you know in process. Thank you.

‍

Nico Johnson  47:35

Congrats on all the success. Honestly, like I what what I'm asking myself is like, how many of the companies I'm investing in could go the route that you're going? Like, could still even seek non dilutive capital like this?

‍

Charlie Murray  47:47

Yeah, and I I've coached some companies very recently to just say like, you know, they're they're a company companies out there that don't have like the goalposts for us were originally like, okay, make sure you have a working product, and then once we did that, it was like, oh no no no we meant working in the field with a utility and then it was like well no actually we meant the utility says they're going to buy more and I was like well actually we we meant that the utilities already cut you the check and you're revenue generating and that was kind of like the the goalposts moving for us throughout you know we've been around for for 10 years now yeah feel like if I'm wrong if

‍

Nico Johnson  48:19

I'm that far along why do I need you? Yeah,

‍

Charlie Murray  48:20

yeah. So, I mean, so so here's here's the rub. It's like you you can't fund growth of an operations and sales team based on these grants. And it was just released, you know, yesterday that we we actually did end up raising our first you know round. And it's funny that you mentioned ABB earlier. So ABB is a part of it,

‍

Nico Johnson  48:40

strategic. Yeah,

‍

Charlie Murray  48:41

yeah. As long, of course,

‍

Nico Johnson  48:42

they would want to be.

‍

Charlie Murray  48:43

Yes, I mean, we've got a few strategics in there. So there's another couple great companies, Southern States and Southwire, who are also in.

‍

Nico Johnson  48:51

Yeah, Southwire being one of the largest conductor providers in the U.S. Yes,

‍

Charlie Murray  48:55

and an interesting partner for us, right? Because our our main you know competition when we're talking to utilities, is reconductoring the lines? You know, just throwing millions of dollars of conductor wire at at the problem. So we're we're really excited about those folks, as well as you know the there's some VCs in there that really see the vision and are. They must be really

‍

Nico Johnson  49:13

flattering though, of like companies like ABB and Southwire acknowledging actually if this works, it's going to cut into our margins and our revenue opportunities. We should get. We should figure out how to get involved in this.

‍

Charlie Murray  49:25

Yes, I mean if that feels good, it also you know it helps us on a few different fronts. On the investment front, a lot of VCs aren't terribly comfortable with the utility markets, and those companies know utilities. And so when they're buying into this, it helps get other investors, you know, across the finish line. And then the other thing that I would say about it is, you know, even the utilities sometimes they just don't have bandwidth to really understand. Like, is this a credible solution? Should I be spending time on it? And yeah, you need to help with that. Exactly.

‍

Nico Johnson  49:56

So we've established why the problem exists and why you believe there was a. Way to solve it. Obviously, now you've convinced others that there is a better way to solve it. I'd like to get practical. If I'm a developer, utility planner, how does this technology actually do something useful for me? So, you've mentioned that some projects could be installed in a few months and potentially unlock one or two megawatts of additional load serving capacity in prior conversations. What determines how much capacity you can actually recover, and what does that mean for someone who, like many of our listeners, is trying to think about serving the grid in a similar way?

‍

Charlie Murray  50:32

Yeah. So I would say, getting back to it, what we find is that there's constraints that pop up first, and so like the the lowest hanging fruit in terms of constraints, usually there's voltage constraints. Usually, those voltage constraints show up on one phase, and then as you exceed that, you'll start to get to thermal constraints, which is you're overloading a wire, and and that is where you know you're going to start reconductoring the circuit. And if you know developers or you know anybody who's connecting loader generation, you know hears those things, interconnection upgrades, and it usually carries two things with it that are are really project killers. One is cost; the other is time.

‍

Nico Johnson  51:09

Yeah,

‍

Charlie Murray  51:10

and so our device is a much faster way to unlock that capacity. So let's get into the numbers a little bit about what that looks like. You know, our cost compared to a reconductoring, you know, we're usually like 1/6 or less the cost of reconductoring. Reconductoring is typically on the order of a million dollars per mile, is what we see for for overhead with with like big investor owned utilities. When we go to utilities that have underground, that number goes up three to 5x. Oh yeah. So and by the way,

‍

Nico Johnson  51:42

many utilities are trying to go underground for a lot of other safety reasons. And

‍

Charlie Murray  51:47

yes, wildfires. You know, from a reliability perspective, okay, underground, we get it. It makes a ton of sense. It's just expensive, and it comes back to this cost trade-off question, right? And then when you're overloading those those systems, and it's like, well, we have to go and you know pull conductor out of ducts, or if it's direct buried, you know, it's it's also pretty complicated. You know, you're talking about a lot lot of outages for customers. It's money, it's time. You're ticking people off. There's a lot of NIMBY putting a four foot by nine foot box in the ground. You know, it takes a day to install our equipment. There's no outages required for customers, and you're going to get similar results in terms of how much increased capacity you get on that line. That is the the sort of like speed to power, you know, if you want to call it that, or speed to interconnection that we can offer. That is something that we'd love to see, you know, partnerships with different developers and folks that are are looking at interconnection costs and how they're so. What does it mean for

‍

Nico Johnson  52:42

a solar developer? Like, let's someone who's developing solar and battery projects in New York, where you've got a lot of experience. How can they leverage this new sort of capacity or knowledge that it exists?

‍

Charlie Murray  52:57

Yeah, I would say you're pushing for for understanding what the limits are and what's triggering those interconnection upgrades, and seeing if it if it does tie to thermal constraints or voltage constraints on different phases. Understanding you know what type of constraint that is is important. What we can bring to the table is you know anywhere from an extra megawatt to two and a half megawatts of load serving capacity out of the same circuit, and just by slapping this box in there, that's

‍

Speaker 1  53:23

amazing.

‍

Charlie Murray  53:24

On the generation side, it would say 500 kW up to a megawatt of additional generation capacity that you can put on on the same circuit. That's what we've seen through you know distribution planning studies that we've done, and not just the planning studies. We've actually done the planning studies, put the boxes in the field, measured the results, benchmark them against the studies, and show that like it's accurate. And that's all in the public domain too.

‍

Nico Johnson  53:46

Are developers sort of taking you in with them to talk to utilities, or like I'm I'm still trying to figure out like the commercial relationship that maybe is beneficial for you to someone that's trying to evaluate this for themselves.

‍

Charlie Murray  53:58

Yeah, I would say we're still early days on that, you know. And and to to be brutally honest, is like we we kind of feel like you know we wanted this to be a utility tool in the toolkit, and we also know that developers are tenacious. I feel like is a good word for it. I used to be one, and I'd like to think that I was tenacious. I mean, developer an

‍

Nico Johnson  54:18

extra BD resource for you at this point.

‍

Charlie Murray  54:20

That's I think that's the idea here. Is it's like you know, if if folks want to push down this path of how can we squeeze more down this circuit, you know, asking to evaluate you know dynamic phase balancing as a way to do it to unlock extra capacity. And I'm thinking about you know not just new projects, but let's say you have projects that are getting curtailed like crazy. Like it's another opportunity where it's like, hey, could we evaluate how curtailment would change if we're the wrinkle that we

‍

Nico Johnson  54:47

haven't talked about, Charlie? That's existing operating assets. Okay,

‍

Charlie Murray  54:51

yeah, it's interesting.

‍

Nico Johnson  54:52

So let's stay with the development for a second. Most developers only learn that there's a distribution constraint when their interconnection study comes back with an. Costly upgrade or a denial. What should they be asking the utility earlier? I

‍

Charlie Murray  55:05

mean, I would say asking for for understanding where those constraints are. Like, you know, utilities sometimes want to share details, sometimes they don't. I think evaluating if there's additional automation equipment, including dynamic phase balancing that could unlock more capacity is is kind of an ideal path, and it's going to be again, it's just going to be lower cost. I hope trying to reconductor the. I hope

‍

Nico Johnson  55:30

you have a big customer service, aka sales and business development team, because my listeners are going to be calling you trying to answer all these questions for themselves now. Yeah, and I think we

‍

Charlie Murray  55:39

want to educate folks. This is, I mean, this is a little bit of our coming out party on on this concept because we have historically just been so focused on like, hey, this is a utility tool; it belongs in the utility toolkit, and you know, we're excited to educate and share this with others.

‍

Nico Johnson  55:52

Fantastic! And you've got a leg up on something they don't, which is utilities don't want to be told how to engineer their systems.

‍

Charlie Murray  55:58

Correct, by especially

‍

Nico Johnson  56:00

by these snot-nosed developer kids that that have no clue how utilities work, right? Like you're selling, trying to sell their projects. How do you address that?

‍

Charlie Murray  56:10

I mean, the other side of the coin here is like this should make the utility operators' lives better.

‍

Nico Johnson  56:15

Should you know? It's but it's presumptuous at best. It it

‍

Charlie Murray  56:19

it's it's a little presumptuous, but if if you think back, so let's let's take this down the use case rabbit hole a little bit. Utilities, you know, have to maintain power quality. They, you know, that is something that's on them. As loads become more volatile, it gets harder for them to chase around these power quality issues. And a lot of those, if you think about the utility business model, they're opex issues. You're sending troublemen out there. They're going try to manipulate the lines. It's hard to solve for them. They're recurring. You know the benefits of our devices. We're going to get those extra capacity, those extra electrons down the pipe. That's good for utilities too. They want to sell more electrons. You know, and they want to sell them quicker, right? That speed to power is something that's not lost on a lot of utilities. And then the last piece of it is from a reliability and resiliency perspective, most utilities are thinking hard or have already deployed some type of system restoration, you know, automation. And our box is phenomenal at levering up the benefits associated with that and making it easier for them to restore the system and understand what's happening on the system. You know, driving down how complex it is to restore service to customers. It's like we we are a good citizen to the utilities, and a lot of them are moving on their own to to adopt the device. Yeah, you know, and you know if we can help some developers in the meantime, we'd be thrilled.

‍

Nico Johnson  57:35

I'm curious where you find yourself now. You've just raised a round. You spent the last 10 years for reasons that we discussed, basically not following the traditional venture capital playbook to start the company. Why now go to the venture capital route? Because because it sounds like let's just add on to that. Because it sounds like utilities are buying, and you could potentially cash flow the company. Like

‍

Charlie Murray  57:58

yeah, we we fell a little short on that front, right? So we, I think there was a window there where we we thought that we could glide path into cash flow positive, and that was you know you know for the entrepreneurs on the call like that is an exciting you know light at the end of the tunnel. Yeah. The other you know problem with businesses like ours is like they can grow very very big very very quickly. You need to be able to accommodate that growth, and the reality of building hardware is you need capital to be able to grow quickly. And so, you know, it was kind of funny because it's like we're going out to market talking to VCs, and it's like this is a Series A round, but it's a growth round. Yeah, it's it's a Series A round, but we're revenue generating. You know, it's like that is also something that like we saw people continue to raise these monster mega rounds, and and good for them, you know. And and I think again for the entrepreneurs out there, what we have found is, if you're Series A, you're raising $100 million or you're raising $17 million, you know, chances are you're going to take similar amounts of of dilution, which is crazy, but it's just how the game works.

‍

Nico Johnson  59:02

Wow! For

‍

Charlie Murray  59:02

us, we knew that we couldn't grow the operations and sales side of the business to where we needed to be without taking on investment.

‍

Nico Johnson  59:10

Yeah,

‍

Charlie Murray  59:11

and so we did that, and we tried to do it with the right folks. Was was kind of the key thing for us. It's like we wanted strategics, and we wanted folks that really got comfortable with our counterparts being utilities, and I would love to say that this was on purpose, but it wasn't. You know, the the thing that kind of hit that was interesting is, you know, data centers have been driving this conversation around affordability, and affordability got translated to regulators and legislatures at the state level as utilization. Our utilities utilizing the existing infrastructure they have, and that is us. Like we are the utilization tool for distribution. We just are.

‍

Nico Johnson  59:50

Yeah.

‍

Charlie Murray  59:50

And that is something that's like an exciting happenstance that's just going to pour you know gas on the fire here.

‍

Nico Johnson  59:56

So what I heard you saying, Charlie, which is a wonderful place to be as an entrepreneur. Is that there's just there just aren't other companies solving this problem the way you're solving it. You're like a one of one.

‍

Charlie Murray  1:00:06

We are a one of one, and I think it has to do with like it takes a lot of brain damage, you know, to to develop these tools. And maybe we were the only people that were dumb enough to set out on this path, you know, 10 years ago.

‍

Nico Johnson  1:00:20

Well, I'll ask a question that sort of follows that line. What's a? I appreciate any. I mean, all all entrepreneurs that have gone through a decade of building are self-effacing. What's a decision you made along the way when you look back on it? You'd handle it differently.

‍

Charlie Murray  1:00:37

There was something that we decided early on. We we we had one of these kind of one-off conversations with the utility about what that initial product needed to look like, and they painted a picture that was like a very high bar and not a true MVP. Yeah, we we chase that, and that hurt us in a big way. And it's not that person's fault; they're probably right. It's just you know you have to sometimes you have to listen to the customer, and sometimes you have to you know listen to you know some of the traditional wisdom around what is an MVP? How do you get to market? So there's a little bit of push pull there, and we just ended up on the wrong side of that one. And then I think the the better decision that we made was, you know, we we did have some customer discovery, which put us on this phase balancing path. And it was interesting enough to us, even with our meager resources, that we're like, we should we should figure out a way to chase down this path. Let's just get a little bit smarter and move the ball a little bit in this direction. Yeah. This this wasn't like a wake up one day pivot and you know that other product died. It was a you know can this be in an and? And then it quickly became clear that it's like oh this is this is actually the the mainstay. This is the primary. I

‍

Nico Johnson  1:01:40

want to finish wrap the conversation looking at what all this means for kind of looking for the next generation, our energy infrastructure, and and how we build it. As more solar storage and distributed energy resources get connected to the grid, how do you expect the distribution grid's challenges to change or evolve?

‍

Charlie Murray  1:01:59

I have this vision for for a grid that sort of breathes, and and what I mean by that is, you if you look go back to those solar hosting maps or early days and what you know convinced us that there was a problem here, it's like that that vision that I showed is like, hey, downtown areas, it's tough for them to, you know, to develop solar in downtown Chicago, like it's just it's not going to happen. We're not going to build you know 20 acres of of solar in downtown Chicago, and we have transmission systems which which can help move electrons very very freely. But at the distribution level, you know, we should also be able to move those electrons and share them between substations and have sort of this like homogeneous picture of these you know rings where it's like yeah it's harder to get the solar into the downtown, but maybe the downtown breathes in it kind of inhales and we're able to help transport those electrons in through the distribution system without sacrificing reliability, and I think that's something that like we want to get to is like utilities again are planning for worst cases they're planning for that summer peak, and we want to see you know more leverage of the full assets on a day to day basis. You know, getting the electrons or oxygen, you know, where it needs to go, and creating tools for utilities so that the grids can be more flexible and dynamic. and And I think we're we're actually pretty close to it. Like we're you know that's like a maybe like a 10 year vision sort of thing, but I think we're pretty darn close.

‍

Nico Johnson  1:03:25

For another founder listening who's inspired by you and is therefore prone to listen to advice you might give, you know a lot of folks building capital intensive energy technology businesses that that tune in to SunCast. What's a lesson that you wish someone had taught you before you started the business that you had to learn the hard way as an entrepreneur, and you can pass along to others. Learn from my mistakes.

‍

Charlie Murray  1:03:48

You know, I I don't want to break my arm off patting ourselves on the on on my back, but like we we tried to establish those dialogs with customers early on, and I think that that's critical. And and it can't just be a you throw something over the fence to them. It's like it has to be bidirectional, and then I think the the other thing is like you we we leveraged grants a lot because early days we were scared by companies that were in our space that we had seen go VC too early and then get caught in this like capitalization trap where they could never meet the expectations of what the valuation needed to be because of the VC rounds they had raised, and yet they were selling millions of dollars in equipment and really should be considered successes.

‍

Nico Johnson  1:04:28

Yeah,

‍

Charlie Murray  1:04:29

and so it was just like, is VC the right model for this? And I think you you for for energy tech entrepreneurs, there's lots of VCs that do want to get into the space. Hardware has somehow over the last 10 years, become cool, you know, and so you could probably get that deal. But I think it's it's still a question you should ask yourself. It's like, is this the right fit? Is there a way that I get smarter on you know non dilutive capital before you know jumping into the VC game? And then I think the last thing is just you know people, man. You you've got to surround yourself by the right with the right people. You know that does. Mean that you have to go out and hire 100 people. You can be careful. You can use you know contractors and things like that, but you got to find the right people to help you get it done because these problems are are so complex and they require subject matter experts in like very kind of nichey things that you're going to need to have a deep bench, even if those are like a deep bench of a lot of pinch hitters that can come in when you really need that particular tool.

‍

Nico Johnson  1:05:26

Yeah, yeah. I think people would be surprised, maybe not the founders listening to us, but people generally, with how many contractors operate in early stage businesses, because you really don't have the cash flow or or or even availability to support full time employees, and so everyone's sort of like fractional contributors.

‍

Charlie Murray  1:05:43

Yep.

‍

Nico Johnson  1:05:44

What's a question every founder should ask a prospective investor?

‍

Charlie Murray  1:05:48

Oh man. Oh, this is an easy one for me. A reference.

‍

Nico Johnson  1:05:52

Oh.

‍

Charlie Murray  1:05:53

Um.

‍

Nico Johnson  1:05:54

To talk to someone else they've invested in.

‍

Charlie Murray  1:05:56

Yes. And you know what? A lot of them will blow you off, and and it's because, in in my opinion, they just don't have that strong of a relationship with the folks that they've invested in. Maybe the people, the founders they invested in, are no longer with those companies. Maybe they had something to do with that. Our lead investor that we we had lead this round was was somebody that you know I would say you know not the biggest brand name in the room, and one of the ways that we got comfortable with them was, you know, it was like an immediate check mark in our book was we asked them for references. They got us in touch with three founders within 24 hours, and we were talking to them. And it is, I just can't stress enough. It's like your investors are going to ask you for customer references. They just are. You should be asking them for invest for co-founder references and put a lot of weight on it. Like really put a lot of weight on it.

‍

Nico Johnson  1:06:51

That is fascinating. Yeah. What's the most underrated technology in the distribution grid?

‍

Charlie Murray  1:06:58

Ours. No, I the

‍

Nico Johnson  1:07:01

side switch floors.

‍

Charlie Murray  1:07:03

I you know it's it's a tough one for me to say right now. I think we see a lot of utilities putting a ton of money into automation control systems. These ADMSs. It's good to know what's going on on the system.

‍

Nico Johnson  1:07:20

Yeah.

‍

Charlie Murray  1:07:21

You know, AMI has been deployed once. I forget what you know number point zero of AMI we're on right now, and maybe it's just 3.0. But like people keep talking about the next generation and what it's going to do. At some point in time, you don't need sensors and measurements. You need to go out there and do something with

‍

Nico Johnson  1:07:35

it.

‍

Charlie Murray  1:07:35

And you know, I do. I love the idea of you know some of the VPPs. I love the ideas of you know just getting more solar out on the grid and creative ways, either you know regulatory structures or you know fast interconnections and all the work that's being done there. You know reclosers have been like a big thing where like utilities have plowed tons of money into automated switching. There's you know these great single phase reclosers that work on laterals.

‍

Nico Johnson  1:08:03

Yeah.

‍

Charlie Murray  1:08:03

Um. So there's there's just it's like I mean they're not my children they're not my ideas but it's like tough to name a favorite. Uh. You know they. I think the the thing that I would get back to is like I have developed more of a a love for technologies that can provide a lot of value without telling them what to do.

‍

Nico Johnson  1:08:22

Yeah,

‍

Charlie Murray  1:08:22

and you know, of course, we fit in that category, and that's probably my bias. You know, where you can set this up, and it just can make decisions that are going to help the grid. But I think the more communication links and cybersecurity that's required, and coordination and complexity associated with that, yeah, the harder it is to rely on it and to get the reliability that you need out of it, and it's just I I I don't know how to separate those two things. I wish that there was an easy solve for it, but it's just tough

‍

Nico Johnson  1:08:50

for folks that want to connect with you. How do you like to be found? It's easiest way to touch base.

‍

Charlie Murray  1:08:56

Yeah, you can find me on LinkedIn. I'm actually pretty darn responsive on there, and then, also you know, go to our website and you know our website is www. switchsource. com. Switch

‍

Nico Johnson  1:09:06

switched ed. Switch switched

‍

Charlie Murray  1:09:08

ed. S W I T C H E D source. You know, get on our website. There's some forms in there and there's some information in there for you to engage with. And I think if you're interested in learning more and getting in the weeds, you know, company like ours, we got loads of content, we got loads of use cases and things like that, and we're always happy to to kind of share it and talk about it.

‍

Nico Johnson  1:09:27

As you look out over the next five years, what will have changed as a result of the work that you're doing?

‍

Charlie Murray  1:09:32

I think that we're going to see utilities embrace system utilization. I think that there's a little bit of a carrot and a stick that's that's showing up right now with the regulators and thinking about this, and you know, I think once the utilities kind of realize, oh my gosh, like there's, you know, there's this one piece which is like my mainstay of planning for peak, and then I'm doing my my business as usual, capital planning, putting wires in the ground, and it's like that and operation. Are a lot of times different verticals inside the utility. Once they realize that better system utilization and the tools that we're bringing to bear help a ton on operations and make their lives easier in ways that they weren't thinking about, that is what I think we're going to see is like really like is the aha moment for the utilities over the next five years.

‍

Nico Johnson  1:10:19

Charlie Murray is the founder and CEO of Switch Source. Charlie, I appreciate you taking us behind the engineering and business of making our grid smarter. Appreciate you joining us here on SunCast.

‍

Charlie Murray  1:10:30

Thanks, Nico. Appreciate the invite.

‍

Nico Johnson  1:10:32

I think the biggest takeaway here for those of you still listening is that solving our energy infrastructure challenges isn't always about building more, despite our predilection to do so, sometimes it's about understanding the system that we've already got in front of us and finding ways to make it work for us in new ways. For developers listening, I hope that this changes the questions you're asking your utilities about interconnection and grid constraints, and even your engineers on your own team about how they think about solving these problems. And for entrepreneurs listening, Charlie's journey is a reminder that building meaningful infrastructure technology requires more than just a great idea or great invention. Takes patience, partnerships, and the right kind of capital. Not always the first one that shows up or the first one that you wanted. You can learn more, as he said, about the work that they're doing at SwitchSource.com. We'll link to Charlie and all of his other ways to connect with them in the show notes. I also want to say thank you to those who help support the show. Our sponsors, they pay the bills and help keep the lights on. All we ask you to pay is attention. You've done that diligently through the last almost 90 minutes, and I'm honored by it. If you would honor me by taking a moment to check them out. That would be so so super helpful. They can be found at SunCast media forward slash sponsor. It's also how you could find ways to reach the 1000s of solar warriors and climate champions that tune in just like you to sharpen their saw and put another tool in their toolset each and every week, twice a week, just like you did today. Remember, you are what you listen to. Thanks again for showing up, Solo Warrior. It's half the battle.

Nico Johnson

Entrepreneur & Podcaster

In my 20 year career, I've worked with dozens of entrepreneurs, intrapreneurs and professionals in transition to clarify their mission, set or stretch their goals, and work through the barriers to their growth.

We’re Excited to Hear from You!

Don’t hesitate to reach out—whether you’re here to learn, share ideas, or work with us, we’re ready to connect.